Ameren Dock Permits and Electrical Inspections at Lake of the Ozarks
At Lake of the Ozarks, Ameren Missouri permits docks, seawalls and breakwaters. Work cannot start until the permit is issued, a certified builder or the owner must build, a new dock or modification costs $550, and docks with power need a fire district electrical permit and inspection. Call (573) 410-4467 for help with your project.
Ameren Missouri owns Bagnell Dam and manages the shoreline of Lake of the Ozarks, so it, not the city or county, permits docks, seawalls and other work on the water. Here is how the process works, based on Ameren's published rules. Call (573) 410-4467 to reach a certified builder who can handle it for you.
Step 1: Use a certified builder (or do it yourself)
Docks, breakwaters, additions, modifications and re-foaming must be done by an Ameren Certified Dock Builder or the property owner. Certified builders carry at least $1,000,000 of liability insurance naming Ameren, workers compensation and employer liability of at least $500,000, prove proper foam disposal and pass inspections.
Step 2: Gather what the application needs
- A copy of the fire district permit or electrical approval, for docks with power and for pumps.
- Drawings to scale on 8 1/2 by 11 inch paper.
- The location of the work inside your property lines extended lakeward.
- For a dock: distance to those property lines, distance from the end of the dock to the channel or cove center, distance across the channel or cove, distance to the nearest dock on each side, and dock dimensions.
- For bank stabilization: the lowest elevation of the work, distance from the toe of the bank to the seawall, and wall height.
Ameren may also ask for a survey. Work lakeward of elevation 658.5 feet or in a wetland may need U.S. Army Corps of Engineers approval, except boat docks.
Step 3: Apply online
Applications go through Ameren's online permit portal. Homeowners apply directly, or authorize a certified builder or realtor to apply for them. Ameren reviews for completeness and shoreline rules and may ask other agencies to comment. Construction may not start until the permit is issued.
Step 4: Pay the fees
| Activity | Fee |
|---|---|
| New dock or modification | $550 |
| Bank stabilization | $300 first 100 ft, plus $1 per foot over |
| Breakwater | $1,000 |
| Pier | $100 |
| Steps | $50 |
| Boat ramp | $300 |
| Dredging or excavation | $500 |
| Pump, 2 HP or less / over 2 HP | $75 / $100 |
| Permit transfer / extension | $100 / $50 |
| No permit, or not following permit conditions | $2,000 each |
Docks over 3,000 square feet pay an annual fee of $0.06 per square foot of water space, including slips, lifts, ramps and breakwaters.
Step 5: Build within the deadline
Docks and breakwaters must be finished within one year of the permit, with one six-month extension if nothing changes. Bank stabilization, piers and excavation get two years, with no extensions. Expired permits are void and need a new application and fees.
Electrical permits and inspections
Docks with power need an electrical permit and inspection from the local fire protection district, with a fee paid to the district. Ameren's dock wiring checklist includes:
- A sub-panel at the seawall next to the dock ramp, with a disconnect.
- A 4-wire feeder for 240-volt systems.
- Liquid-tight flexible conduit at all pivot points.
- GFCI protection on all receptacles, and marine twist-lock GFCI outlets for equipment.
- A disconnect within 30 inches of an equipment outlet or an approved pedestal.
- A ground rod at least 8 feet long and 1/2 inch, and #6 bonding jumpers across pivot points, stiff arms and breakwaters.
On a property sale, the dock's electrical inspection must have been completed and approved within the previous 12 months.
Why it matters
In July 2012 three people were electrocuted at the lake in a single week. Ameren's shoreline manager urged owners to have docks inspected regularly and said keeping a dock electrically safe is each owner's responsibility. If anyone feels a tingle in the water, swim away from the dock, shut off the power and call an electrician.
Ready to start? See our new dock construction page or call (573) 410-4467.
Call and we will connect you with an independent local provider.